The Dutch construction sector still has plenty of work, but that does not automatically mean projects get off the ground quickly. The real brake at the moment is not on the demand side, but mainly in execution. Staff shortages, nitrogen, grid congestion, permits and growing complexity mean the sector sees opportunities but cannot always realise them at the desired pace.
That picture is confirmed by several reliable sources. In its sector forecast of September 2025, Rabobank noted that value added in construction shrank in two consecutive quarters, while less than 10 percent of companies said they were affected by insufficient demand. That indicates that mainly supply problems are holding the sector back.
Not too little demand, but too many obstacles in the construction sector
The construction sector remains a sector with a strong underlying need. Housing construction, sustainability, renovation, infrastructure and an ageing population all create a structural task. At the same time, practice shows that a full order book is no guarantee of progress.
For companies, this means project risks increasingly arise outside the project itself. Not only in material prices or planning, but also in permits, energy connections, staff and administrative procedures. As a result, attention is shifting from purely organising capacity to integrated risk management.
Staff shortages remain the biggest operational brake in the construction sector
One of the most persistent bottlenecks is the labour market. According to Statistics Netherlands (CBS), more than 80 percent of entrepreneurs in the construction sector said in April 2025 that they were experiencing a staff shortage. That made construction the sector in which labour shortages were mentioned most often. CBS also reported that construction had the highest vacancy rate of all industries in 2025.
That shortage has direct consequences for execution. Projects are harder to scale up, production is sometimes limited to what is feasible with the available people and companies have to choose more carefully which contracts they do or do not accept.
Permits remain a vulnerable point
The pressure also remains high at the front end of the construction chain. CBS figures showed several signs of delay in 2025. In the second quarter of 2025, permits were issued for the construction of 20 thousand new homes, 3.3 thousand fewer than in the same period a year earlier. The number of permits for commercial buildings also fell. CBS also reported that the number of permitted temporary homes in the first half of 2025 had almost halved compared with a year earlier.
Figures like these are important, because permits are a leading indicator of future production. Fewer permits today often mean less completion tomorrow. For construction companies and chain partners, that makes it harder to organise investments, staff and planning ahead with confidence.
Nitrogen continues to affect permits and pace
The nitrogen issue remains a slowing factor. Rabobank explicitly named nitrogen as one of the causes of the decline in construction activity. The EIB also concluded in 2025 that new nitrogen rules affect housing construction. At the same time, the government is trying to keep the construction sector moving. In September 2025, the Ministry of Infrastructure and Water Management reported that more than 120 local and regional authorities now take part in a scheme that encourages the use of cleaner construction equipment, precisely to let construction projects go ahead despite nitrogen restrictions.
That is positive, but it also underlines that the sector will have to keep working in an environment where permits and regulation largely determine pace and feasibility for the time being.
Grid congestion increasingly affects the construction sector directly
Besides nitrogen, grid congestion has also become a structural construction problem. According to the Dutch government, a connection to the electricity grid is an essential precondition for a well-functioning economy. The Netherlands Enterprise Agency (RVO) also warns that grid congestion delays growth and sustainability plans and also affects housing construction and business parks.
For construction, this has several consequences. New projects can be delayed by a lack of grid capacity, development sites become harder to realise and sustainability ambitions sometimes clash with the limited room on the electricity grid. Part of the risk is therefore shifting from the building site to the energy infrastructure around the project.
Still, there is also a positive outlook
So the picture is not only negative. The EIB expects a clear improvement in housing production in 2026. After 68,000 homes were completed in the previous year, the institute expects around 80,000 completions in 2026 and 84,000 in 2027. The Dutch government also sticks to its ambition to increase housing construction towards 90,000 to 100,000 homes a year up to and including 2030.
In addition, the cabinet is working on extra measures. In April 2026, the government reported that provinces are deploying more capacity to adopt and permit plans faster. In March and May 2026, extra boosts were added for heat networks, homes for older people and the acceleration of housing projects.
That combination shows that the demand fundamentals of the sector remain intact. The need for homes, renovation and sustainability is still there. But execution requires more coordination, more predictability and more control over risks than before.
Financial control becomes more important in a slow chain
Precisely because projects have longer lead times and decision-making can be more sluggish, the financial importance of good project management also increases. If permits are delayed or completions are postponed, invoicing moments, cash flows and planning pressure shift too.
That is why it is not enough for construction companies to plan well operationally. Especially in a sector where margins are often under pressure, predictability makes the difference between temporary delay and structural strain.
The construction task is huge, but execution remains the key
All in all, the current situation shows a mixed picture. The construction sector has no shortage of work. On the contrary: the social task is enormous. But between ambition and realisation there is still a broad layer of obstacles.
The coming period is therefore less about whether building is needed, and more about how projects can be realised faster, smarter and in a manageable way. That requires not only extra building sites and permits, but also more clarity, capacity and feasibility.
For many construction companies, the biggest gains in the coming years therefore lie not only in more production, but above all in more predictability.
Sources and background:
- Rabobank sector forecast September 2025 (Dutch)
- CBS on staff shortages in construction (Dutch)
- CBS on permits for new homes and commercial buildings (Dutch)
- CBS on the housing stock in 2025 (Dutch)
- EIB: construction output and employment outlook 2026 (Dutch)
- Dutch government on accelerating housing construction (Dutch)